Progress on Project Bright beamlines

The complex engineering of scientific instruments is explored in this ‘behind the scenes’ look at the installation of frontends for two new beamlines at the Australian Synchrotron.

Good progress has been made on the installation of supporting infrastructure for the first of the new beamlines for the Australian Synchrotron as part of Project Br–ght.
The work is a series of complex engineering tasks that require precise planning, the expertise of applied mechanical engineering, controls engineering and supporting technicians.
Importantly, the majority of installation works could only be done during periods when the synchrotron was not operational.

Installation of the ‘frontends’ for two new beamlines, Medium Energy X-ray Absorption Spectroscopy (MEX) and Biological Small Angle X-ray Scattering (BioSAX) is now complete with final commissioning tasks on schedule. Completion is expected during the coming Christmas shutdown, according to Senior Engineering Manager Brad Mountford.
The ‘frontend” is the physical conduit that carries powerful synchrotron light from the main storage ring through the shield wall that surrounds the ring.